What the auditor opens before he opens the breaker

A utility procurement engineer receiving three bids for the same 145 kV bay reads the technical offer in a fixed order: ratings, then the drawing, then the KEMA type test report. The first two tell him what you claim. The third tells him whether anyone independent has ever proved it. It is at that moment that otherwise identical offers separate, because a type test report is not a certificate of good intentions — it is a document with a laboratory’s accreditation behind it, a defined scope of validity, and a list of variants it does and does not cover.

This article is written from the buyer’s side of the table, because that is where the questions come from: what documentation a tender actually requires, how KEMA and the STL system differ from a domestic CNAS report, which clauses decide whether your model is covered, and the defects that experienced auditors treat as disqualifying. The short version — a high voltage SF6 circuit breaker type test report is a claim about a design, not about the unit you are shipping. Everything difficult about reading one follows from that sentence.

Type test, routine test, field test: three different promises

Buyers who have been burned once learn to separate three documents routinely conflated in a sales pack. They are produced by different parties, at different times, on different objects.

DocumentObject testedWho issues itThe question it answers
Type test report / certificateOne sample of a design, usually destroyed in the processIndependent accredited laboratoryIs this design capable of the rating at all?
Routine test reportEvery single unitThe manufacturer’s own test bayWas this particular unit built correctly?
Field / commissioning recordThe installed unit on siteCommissioning contractorDid it survive transport and installation intact?

The tiers are not interchangeable. A factory that has run dielectric and resistance checks on ten thousand units has proved nothing about whether the interrupter can break 40 kA — only a short-circuit laboratory can prove that, and it destroys the sample doing it. Conversely, a beautiful certificate says nothing about whether the breaker in crate 3 was assembled with the right gasket. This is why an auditor asks for both, and why he checks that the routine report references the same design the type report covers.

Diagram of the three test tiers from design proof to build proof to field condition proof
A certificate proves the design, a routine report proves the unit, a field record proves the installation – no single document covers all three.

Who KEMA actually is — and why the name is confusing

KEMA is not a company any more, and this trips up buyers who try to verify a certificate against a corporate registry. The original N.V. KEMA was founded in Arnhem in 1927 as the Dutch electricity industry’s testing institute. It was later split, and the parts went to different owners. KEMA Labs — the high-power and high-voltage laboratories — is now a business unit of the CESI Group, operating facilities in Arnhem, Milan, Berlin, Prague and Chalfont (Pennsylvania), with three-phase short-circuit capability from roughly 2 000 MVA up to 15 000 MVA and test capability to 1 200 kV. KEMA Quality — the management-system certification body — was acquired by DEKRA in 2009 and issues ISO 9001 certificates under the DEKRA Certification name. DEKRA separately acquired VEIKI-VNL in Budapest in 2017.

So “we have KEMA certification” can mean three completely different things: a high-power type test certificate from Arnhem, an ISO 9001 certificate from DEKRA, or a factory inspection report. Only the first proves breaking capacity. An auditor will ask for the certificate number and the issuing laboratory location before he reads anything else.

What STL adds, and why it matters more than the logo

The Short-Circuit Testing Liaison is an association of independent high-power laboratories, of which KEMA Labs is a founding member. Its importance is not brand prestige — it is the STL Guides, harmonised procedures that dictate how a type test is performed and, just as importantly, how the resulting certificate is written and what it may claim. Because members test to the same guide, a certificate from one member is normally accepted by the others and by utilities worldwide. That mutual recognition is the practical value: a manufacturer testing at KEMA in Arnhem, VEIKI-VNL in Budapest, IPH in Berlin or CESI in Milan is buying a document a Dutch, Kenyan or Chilean utility will accept without re-testing.

The distinction that catches buyers is between a Type Test Certificate and a Report of Performance. Both come from the same laboratory, carry the same letterhead, and are not the same document.

DeliverableWhat it containsWhat it does not contain
Type Test Certificate (complete)Statement of compliance, full test series, covered-variant statement, certificate numberNothing — this is the document to ask for
Type Test Certificate (single performance)Compliance statement for one characteristic onlyDielectric, temperature rise, mechanical endurance
Report of Performance / Type Test ReportMeasured data, oscillograms and test circuit, faithfully recordedAny verdict. It records what happened; it does not certify compliance
Design Verification ReportAssessment by calculation against a tested reference designPhysical test evidence for the variant assessed
Certificate of Conformity / Inspection ReportThat a unit or batch matches a specificationDesign capability

A Report of Performance is not a trick — sometimes it is exactly what is needed, for example when a utility wants the actual oscillograms behind a claimed T100a duty. But if the tender asks for a certificate and receives a report of performance, the bid is technically non-compliant, and an auditor will say so in one line.

The sections every IEC 62271-100 report must contain

The structure is not arbitrary. Each section exists because a buyer, at some point in the last fifty years, was deceived by its absence.

SectionWhat to verifyWhy it matters
Identification of the tested objectManufacturer, type designation, serial number, drawing references, date of manufactureLinks the certificate to a design, not a family name
Rated characteristicsUr, Ir, Isc, tk, BIL, PF withstand, SF6 pressures, massMust match the offered datasheet digit for digit
Standard and editione.g. IEC 62271-100:2008 + AMD1:2012, or :2021Ratings and test duties changed between editions
Laboratory and accreditationLaboratory name, location, ISO/IEC 17025 scope, accreditation bodyAn out-of-scope test is not an accredited test
Test circuit and methodDirect vs synthetic, circuit diagram, TRV adjustment, earthingDetermines whether the duty was genuinely equivalent
Measured quantitiesCurrents, voltages, times, temperatures, gas data, calibration referencesThe numbers behind every claim
OscillogramsMaking and breaking records, arc duration, TRV tracesWhere inconsistencies hide
Statement of compliance and covered variantsExplicit list of ratings and variants coveredDecides whether your model is included

Reading the variants-covered statement properly

A type test is performed on one sample at one rating. No laboratory will test all the 40 kV, 50 kA, 3 150 A and 4 000 A permutations of a family, and no manufacturer could afford it. The standard and the STL guides therefore allow a tested design to cover a family, provided the differences are demonstrated to be non-detrimental. Three patterns are common, and only one is comfortable.

Downward coverage is normal: a sample tested at 50 kA and 4 000 A covers the 40 kA, 3 150 A variant of the same frame, because lower current and lower breaking duty are less onerous on the same hardware — but the certificate should say so explicitly. Upward coverage by calculation argues that a higher rating is covered because the interrupter is identical and only the CT ratio changed; acceptable for some characteristics, not for making-and-breaking. No coverage means the certificate covers one rating and the offered model is a different one, which is the case an auditor looks for and more common than the industry admits.

Practical advice: take the offered datasheet, take the certificate’s variants table, and put them side by side. Every rating in the offer must appear in the table. If a number appears in one and not the other, the question is not “is this a good breaker” but “which of these two documents is wrong”. Two ratings deserve special attention because they are frequently inherited from a sibling model: the 40 kA breaking capacity of a 126 kV frame quoted for a 145 kV variant on the same interrupter, and the 1 050 kV lightning impulse level of a 252 kV design quoted for a variant with a longer column. Both are legitimate only if the certificate says so.

The routine test report: six checks, one number always misquoted

Every unit leaves the factory with its own routine test record, and IEC 62271-1 clause 7.2 defines the minimum set. Auditors read it more carefully than suppliers expect, because it is the only document describing the actual object being shipped.

Routine test (IEC 62271-1, cl. 7.2)What is measuredAcceptance reference
Dielectric test, main circuitPower-frequency withstand, dry, at rated valueNo disruptive discharge
Dielectric test, auxiliary and control circuits1 kV applied for 1 s between circuits and frameNo breakdown; the 2 kV / 1 min value in cl. 6.10.6 is the type test
Resistance of the main circuitDC voltage drop per pole at 100 A or higherNot more than 1.2 × Ru, where Ru is the value before the temperature-rise type test
Tightness testRelative leakage rate of each gas compartmentWithin the limit for the pressure-system type, not worse than the type-tested value
Mechanical operationFive operations at maximum control voltage, five at minimum, plus ratedCorrect sequence, no failure to latch or trip
Design and visual checkNameplate data, markings, paint, corrosion, clearancesConformance with the drawings

The number almost always misquoted is the auxiliary-circuit test voltage. The type test value is 2 kV for one minute; the routine test value is 1 kV for one second. Suppliers routinely print “2 kV/1 min” in routine reports because it sounds stronger. It is not stronger — it is a different test, and an auditor who knows the clause reads it as evidence that the report was assembled from a template rather than by the test bay.

The second number worth checking is the resistance acceptance. The 1.2 × Ru limit compares against a measurement taken before the temperature-rise type test on the same design, not against a generic micro-ohm figure; a bare micro-ohm value with no Ru reference cannot be assessed. On the gas side, the tightness limit depends on the edition cited: recent editions of IEC 62271-1 distinguish a sealed pressure system at 0.1 % per year from a closed pressure system at 0.5 % per year, while older editions allowed 1 % per year. A datasheet claiming “≤1 %/year, fully compliant” is telling you which edition it was tested to — possibly one from before the buyer’s specification was written.

KEMA, STL, CNAS, CMA, ILAC: what each mark actually proves

Buyers in Asia are often offered a report with a CNAS or CMA mark and told it is “equivalent to KEMA”. It is not equivalent; it is a different instrument.

Mark / systemWho it belongs toWhat it provesNormally accepted
KEMA Labs type test certificateCESI Group laboratory, Arnhem / Milan / BerlinIndependent high-power test of the design, STL-guide compliantWidely, including most European and African utilities
STL member certificateAny STL member (KEMA, VEIKI-VNL, IPH, CESI)Same guide, mutual recognition between membersWhere the specification names STL
CNAS-accredited reportA Chinese laboratory within its accredited scopeThe laboratory is competent for the listed methods, report is traceableChina, and buyers who do not specify a laboratory
CMA mark / ILAC-MRAChinese metrology accreditation; international accreditation cooperationLegal validity in China; mutual recognition of accreditationDomestic purposes; supports acceptance but certifies no product
Manufacturer’s own reportThe factoryThat the factory tested its own productRoutine tests only; never a type test substitute

CNAS accreditation is genuinely meaningful, and a well-run Chinese laboratory can produce a report of real technical value. The problem is not the mark, it is the substitution — a CNAS routine test report presented as an independent type test, or a type test performed at a laboratory whose accredited scope covers dielectric testing but not making-and-breaking. The scope document, not the logo, is the thing to read.

Seven defects that make an auditor stop reading

Each corresponds to a failure mode utilities have actually encountered, and each is detectable in under five minutes.

1. The standard edition is missing or stale. A report citing “IEC 62271-100” with no year cannot be assessed. A report citing the 2001 edition against a 2017 specification has a gap that must be closed by a delta assessment.

2. The tested rating is not the offered rating. The certificate says 40 kA, the quotation says 50 kA, the drawing shows the 40 kA interrupter with a larger terminal pad. This is the most common commercial problem and the easiest to check.

3. A report of performance is presented as a certificate. Look for “statement of compliance” and a certificate number. If neither exists, it is data, not certification.

4. The test was witnessed, not performed. “Witnessed by KEMA” on a manufacturer’s own report means a KEMA engineer watched the factory test its own product — a real service, but not an independent type test.

5. Oscillograms missing or generic. Making-and-breaking claims without arc-current records and TRV traces cannot be verified, and identical oscillograms appearing in reports for two different ratings is harder to explain.

6. The sample is not the product. Photographs show a hand-built prototype with machined contacts while the production drawing specifies cast components. The certificate covers the prototype, which is why good specifications require a statement that the sample came from series production.

7. The variants table contradicts the offer. Covered: 2 500 A. Offered: 3 150 A. Nothing else needs to be said.

Two further items are judgement calls rather than defects: a certificate older than about fifteen years, where the design may have quietly changed, and a certificate covering a different frequency (50 Hz vs 60 Hz), where the test duties and TRV are not transferable without assessment.

Flowchart of six verification gates for checking a type test report against an offered breaker model
Six document checks, five minutes each, before the report goes into the tender file.

What a competent supplier sends before the tender closes

The practical test is not whether the documents exist, but whether they can be produced within a day. A manufacturer with a genuine tested design has a folder ready; one without it offers a “certificate in progress” and asks for a purchase order first. A KEMA type test report that arrives as a PDF within four hours of being requested is worth more than one that arrives three weeks later as a scanned cover page.

A complete package for a 145 kV bid contains the full type test certificate with its covered-variant statement, the routine test report for the actual serial number being shipped, the nameplate drawing, the gas schematic with pressure and alarm settings, the mechanism documentation including the anti-pumping circuit, and the packing and storage instructions. On the technical side, the three documents that most often decide the outcome are the breaking-capacity test duties record (T10, T30, T60, T100s, T100a), the temperature-rise test at rated current, and the mechanical and electrical endurance classification (M1/M2, E1/E2) behind the maintenance interval in the offer.

Where a project specifies a design that does not yet exist — a 252 kV variant with a non-standard CT configuration, for example — the correct instrument is not a borrowed certificate but a customized breaker programme with a documented design-verification route against the tested reference design, plus a witnessed routine test on the first unit. Buyers accept that route when it is stated honestly. They do not accept a certificate for a different model with the name changed on the cover.

The gas side deserves its own line. A type test proves the interrupter; it does not prove that the gas in the tank meets specification on the day of delivery. That is covered by the gas quality limits in the routine record — purity, moisture, decomposition products — and a report without those numbers is incomplete regardless of how impressive the short-circuit data is.

Finally, the commercial arithmetic behind all of this. A full high-power type test series at an independent laboratory is a five-figure euro investment and a queue measured in months. That cost is embedded in the price of every breaker from a supplier who has done it, and absent from the price of one who has not. The difference between two quotations for the same rating is often the difference between a manufacturer with test evidence and one selling a design on paper. Understanding that arithmetic is the whole point of asking for the report.

Frequently asked questions

Does a type test certificate ever expire?

Strictly, no — a type test records what happened to a sample on a date. In practice certificates carry an implicit shelf life: a change in the applicable standard edition, a design change to the interrupter, mechanism or insulation, or the passage of a decade or two all weaken the link between tested sample and offered unit. Most utilities therefore require a certificate against the current edition, or a documented delta assessment, and many cap acceptance at ten to fifteen years.

Is a KEMA certificate mandatory for export projects?

Rarely mandatory by law, frequently mandatory by specification. European, African, Middle Eastern and many Asian utilities name KEMA, STL or an equivalent independent laboratory because they cannot audit every factory. Where the specification is silent, a CNAS-accredited type test is often acceptable; where it names a laboratory, substituting a domestic report is a compliance failure regardless of technical merit.

What is the difference between a KEMA type test certificate and a DEKRA KEMA certificate?

The first is a high-power design test issued by KEMA Labs, now part of the CESI Group. The second usually refers to management-system or product certification issued by DEKRA Certification, which acquired KEMA Quality in 2009. Different organisations, different scopes — only the first proves breaking capacity.

Can one type test report cover several breaker models?

Yes, and this is normal. A tested design covers a family of variants where the differences are shown to be non-detrimental: lower rated current, lower breaking current, different CT ratio, alternative bushing. The certificate must state the covered variants explicitly. A report silent on coverage should be read as covering exactly the tested rating and nothing else. If the required test does not exist for your configuration, the honest route is a design verification report against a tested reference design plus a witnessed routine test — not a certificate for a sibling model with the name changed.

How do I verify that a KEMA certificate is genuine?

Ask for the certificate number, the issuing laboratory location and the tested serial number, then verify through the laboratory’s own certificate register rather than through the supplier. STL members maintain verification services precisely because forged and altered certificates circulate. Cross-check the tested rating against the datasheet at the same time — an authentic certificate for the wrong rating is the more common problem.

For the wider picture of how these ratings fit together across the range, see the SF6 circuit breaker technical library, where each rating family is documented against the standard clause that governs it.

Previous Post

SF6 End-of-Life: Recovery, Reclaim, Destruction and the Paperwork That Proves It

Next Post

Shipping, Nitrogen Charging and Site Storage: Protecting a Breaker Between Factory and Foundation

Related Posts

+86-13809159818 Phone xl@hairuielectric.com E-mail Chat on WhatsApp WhatsApp